While
at Tilney Street, I received a letter from Reg Jenkins calling me to a secret
meeting to discuss a possible project. The secrecy of the development was
stressed to David and I as, at the time, Kodak were thinking of moving part of
their factory north and had found a 500-acre site near Nottingham. They were
having Union problems with, in particular, Film Finishing Department at Harrow.
Films could only be processed in the dark and it was difficult to cut and
splice and package in one large hall so not only did the operatives have to
work in complete darkness with tiny light bulbs but the large number of machines
would have to be maintained under very difficult conditions. It was only
possible once a year to open up the hall after all the films had been removed
for yearly maintenance and cleaning. This was not obviously the best solution
to maintain staff cooperation and efficiency. They decided that if they could
get a Green Field site a modern factory could be designed with better
production and a reduced staff.
For
months the proposed development was kept under wraps. Unfortunately, one of my
drawings sent by post to Kodak ended in the wrong hands. Luckily we were not to
blame and anyway the individual that opened the envelope did not realize the
significance of the word ‘Annersley’ and the drawing was passed onto Reg
Jenkins.
It
was finally decided to develop the site and although it was ideal for a future
development, it was adjoining coalfields, which could cause subsidence even
though millers left pillars of support after mining but in time these collapsed
After many meetings, Kodak managed to persuade the National Coal Board that, at
a price, they would not mine under the Kodak site in perpetuity.
We
first designed a general layout for the whole 500-acre site with entrance onto
the main road and internal service roads, car parking areas and a large lake in
the valley and the preservation of a small wood. We had to get approval from
the Severn Trent Water Authority as well as agreeing the position of the sewage
treatment plant.
Before
we could instruct Sir Alfred McAlpine to start levelling the first two plateaus
there was the problem of the 3 footpaths, which crossed the site. The Law of
the Land forbids the interference of footpaths without Ministry approval. It
was necessary to hold a Public Enquiry and representatives from the Ramblers
Association, Friends of the Earth, etc. etc. were there in force and Kodak
employed a QC to represent the company. It then took an age before approval was
given and even then only for one of the footpaths. However it was essential to
start before the autumn and dirty great earthmovers worked around the existing
paths until finally, a few weeks later these were granted after we had
installed an alternative route around the perimeter of the site. The footpaths,
although beautifully constructed, were probably never used!
The
development went ahead satisfactorily although I had a problem with the
structural engineers, Frederic Rand & Partners, who had been appointed by Kodak.
Unbeknownst to me, the firm itself was having a partnership crisis, the senior
partners leaving and the principal's son trying to take control. The first
phase was completed. Each machine in the factory was separated in light-tight
compartments so that maintenance could be carried out without affecting other
compartments. However there was one other main problem, although each of the
compartments were contained with its own air-conditioning, the high relative
humidity required meant that the air in the adjoining areas was laden with
water that condensed with the cold pipes above and the underside of the metal
roof which caused some condensation. This was eventually solved by increasing
the insulation on the pipes and to the roof. I suppose, due to our work
designing Kodak’s laboratory at Harrow, they went on to design the digital
cameras and as a result the demand for film has fallen and I note that, very
recently, the factory has closed.
No comments:
Post a Comment